VX develops hardware from initial requirements through production ramp-up. We design, prototype, test, and deliver the engineering files required for manufacturing.

Our mechanical, electrical, optical, and software engineers test critical functions together, so failures are found in development prototypes rather than after a client has paid for detailed design or tooling.

HOW WE DEVELOP HARDWARE
VX INC. / DEVELOPMENT PROCESS

From requirements to production

VX focuses development effort on the highest-risk parts of a product first. We build and test the critical functions before committing to detailed design or tooling. By finding and resolving problems early, we are able to work quickly, remove unnecessary prototypes, and avoid costly changes later in development.

Development sequence

Industrial Design
Intrinsic Testing
Production Testing
Kickoff Requirements Engineering
Validation
Design
Validation
Production
Validation
MP
Feasibility Study
Extrinsic Testing
  1. Begin ProjectWe have a general idea of scope, budget, and duration for the project.
  2. Stakeholder Sign OffTechnical, business, and financial stakeholders agree on feasibility and what will be built.
  3. Engineering Validation OneNon-form-factor prototypes are built to test individual critical system functions.
  4. Engineering Validation TwoEngineering corrections are incorporated and the affected functions are tested again.
  5. System ValidationComponents are tested together within each subsystem before detailed product design.
  6. Design Validation OneSubsystems are integrated into the intended form factor for extrinsic testing.
  7. Design Validation TwoParts are refined using prototypes and early production tooling samples.
  8. Production Validation (PVT)Production-intent builds are used to resolve issues with tooling, assembly, testing, and yield.
  9. Production Ramp-upManufacturing volume increases while quality, yield, and production test results are reviewed.
REA

Requirements

We begin by defining the product's functional, product, and technical requirements, along with their priorities and verification criteria. Performance targets, budgets, and schedules are established during this phase, and stakeholders review the requirements to agree on what will be developed.

EVT

Engineering Validation Testing

Does the core technology work?

EVT-1 focuses on intrinsic testing, where we develop non-form-factor prototypes to evaluate critical system functions independently. This allows us to investigate the underlying technology without the physical constraints of the finished product.

During EVT-2, we make corrections and engineering changes based on the initial test results. We also validate how the components operate together within each subsystem before committing to detailed product design.

DVT

Design Validation Testing

Does the complete design meet requirements?

DVT-1 brings the subsystems together in the intended product form factor. This is where extrinsic testing begins, allowing us to evaluate how the complete system performs when its mechanical, electrical, optical, and software components operate together.

During DVT-2, we refine the design and validate individual parts for manufacturing. This often involves a combination of prototypes and early production tooling samples.

PVT

Production Validation Testing

Can the product be manufactured consistently?

PVT is an opportunity to resolve manufacturing issues before signing off on volume production. We use production-intent components, tooling, and assembly processes to verify component fit, assembly procedures, production testing, and manufacturing consistency. Problems with tooling, assembly fixtures, test procedures, or production yield can be identified and corrected before production is approved.

MP

Mass Production

Manufacturing begins with a controlled production ramp-up. VX supports the transition by reviewing production test results, monitoring quality and yield, and resolving manufacturing issues as production volume increases.

VX INC. / COST ESTIMATING

Cost estimates through validation

Early test results narrow the range of possible development costs. Once parts, tooling, and production processes have been committed, design changes can require repeating work already completed.

Technology Readiness Level Compliance.

VX helps clients navigate government research programs by meeting the required TRL milestones while keeping commercial product needs, cost, and schedule in view.

Technology Readiness Levels show how far a technology has progressed, from an initial idea through working systems and deployment. VX uses this reference primarily for government research programs, where each step in maturity needs supporting test evidence.

We identify what has been demonstrated and what still needs testing before a client commits to the next stage of engineering. Consumer and industrial product programs typically use requirements and EVT/DVT/PVT validation gates rather than formal TRL reporting.

VX INC. / TECHNOLOGY READINESSTRL 0–9 / Product development reference.
  1. 0 CONCEPT ART · REQUIREMENTS Idea You know the purpose, what it will do or what it will be used for.
  2. 1 Research You know what structure, make-up, or composition is required.
  3. 2 Formulation You know what standards, process, & architecture is required.
  4. 3 NON-FORM FACTOR · VALIDATION Critical Function Validation You have a conceptual offering of critical functions.
  5. 4 Critical Function Prototype Components work in a laboratory environment. (EVT)
  6. 5 PRODUCT FORM FACTOR System Validation You have an integrated system for intended use/environment.
  7. 6 System Level Prototype The system works in the intended use/environment. (DVT)
  8. 7 Demonstration System Operation in pre-commercial scale.
  9. 8 PRODUCTION Production Validation Prototype Commercial process and systems are ready. (PVT)
  10. 9 Commercial Deployment Ready for scale deployment.